Welcome

We are with you every step of the way.

Our sales service does not end once contracts have been signed. We keep our purchasers informed of the development’s progress throughout every stage of the building process.

 

 As we receive construction updates from the developer, we then communicate this information to the purchasers.  It is an exciting process, literally watching your apartment come to life. 

Current Projects

If you are looking for past project updates, please contact:
(03) 9644 2600 or
reception@360propertygroup.com.au

 


 

9 Shuter Street - mOONEE PONDS

  • Developer - CD Group
  • Architect - Jackson Clements Burrows
  • Builder - Balmain & Co
  • No. Dwellings - 61 

Project Update

  • Expected Construction Completion: December 2019
  • Expected Settlement: Early 2020
  • Contact: clinhart@360propertygroup.com.au

October 2018

We are excited to advise you that works are now well underway on site at 9 Shuter Street, Moonee Ponds, with demolition of the existing homes now completed.

{{view_more}
 

Demolition and the basement retention system have now been completed and the anchor system and excavation finished for basement 1.

The completion of 9 Shuter St is currently anticipated for early 2020 with settlement at the property expected to follow shortly after.

For further information, please contact clinhart@360propertygroup.com.au

 


 

303 LA TROBE - Melbourne

  • Developer - Figtree
  • Architect - DKO Architecture
  • Builder - TBA
  • No. Dwellings - 215 

Project Update

  • Expected Construction Completion: Late 2020
  • Expected Settlement: Late 2020
  • Contact: info@figtreeasia.com

January 2018

Preparation and pre-commencement activities for construction of 303 La Trobe are well underway, including obtaining final Construction Management and Demolition Permits required for Construction commencement.


388 Lonsdale - Project Logo

 

388 LONSDALE - MELBOURNE

  • Developer - Aurumstone Pty Ltd
  • Architect - Urban Design Architects
  • Builder - Verve Constructions
  • No. Dwellings - 149 Apartments
 

Project Update:

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: 388lonsdale@aurumstone.com.au

October2018

We are thrilled to announce that 388 Lonsdale has had some excellent progress over the last few months, with the structure now almost complete.  


Adelaide St - Project Logo

ADELAIDE ST - MCKINNON

  • Developer - Citiplan
  • Architect - CBG Architecture
  • Builder - Hutchinson Builders
  • No. Dwellings - 34 Townhouses
 

Project Update:

  • Expected Construction Completion: November 2018
  • Expected Settlement: Late 2018
  • Contact: settlements@citiplan.com.au

October 2018

We are thrilled to announce that construction has been progressing well and we are now approaching completion in late November.


 

 

ALBERT PLACE RESIDENCES - MELBOURNE

  • Developer - Gurner
  • Architect - Elenberg Fraser
  • Builder - Crema Constructions
  • No. Dwellings - 153 Apartments
 

Project Update

  • Expected Construction Completion: Early 2020 
  • Expected Settlement: Early 2020
  • Contact: jessica@gurner.com.au

August 2018

We are pleased to advise that Crema Constructions are continuing bulk excavation works.


 

ATHERTON TCE - GLEN IRIS

  • Developer - Citiplan
  • Architect - BG Architects
  • Builder - Hutchinson Builders
  • No. Dwellings - 11 townhomes 
 

Project Update

  • Expected Construction Completion: May 2019
  • Expected Settlement: June 2019
  • Contact: clinhart@360propertygroup.com.au

August 2018

Construction on site ar Atherton Terrace, Glen Iris is progressing well with the agove-ground structure now taking form.


 

BOAT HOUSE - FOOTSCRAY

  • Developer - Blue Earth Group
  • Architect - CHT Architects
  • Builder - Hamilton Marino
  • No. Dwellings - 193 

Project Update

  • Expected Construction Completion: Late 2019
  • Expected Settlement: Late 2019
  • Contact: kim@blueearth.com.au

July 2018

Boat House, Footscray continues to progress on programme thanks to the hard work of Hamilton Marino Builders.


Brightwood Monash - Logo

 

Brightwood Monash - Clayton

  • Developer - NX Property
  • Architect - Mushan Projects
  • Builder - Valeo
  • No. Dwellings - 129 Apartments and 26 Townhomes 

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

October 2018

Brightwood Monash has been a hive of activity over the past few months with Valeo Construction hard at work.


Casey Green

 

Casey Green - Narre Warren

  • Developer - Osanrae
  • Architect - Demaine
  • Builder - Yarra Bank Homes and Marcus Group
  • No. Dwellings - 58 

Project Update

  • Expected Construction Completion: 3rd Quarter 18 - 1st Quarter 19
  • Expected Settlement: 4th Quarter 18 - 2nd Quarter 19
  • Contact: myeoh@osanrae.com.au

June 2018

We are happy to report that builders have been appointed and construction has commenced for Stages 1 and 2 at Casey Green.


 

 

 

CITRINE - ESSENDON

  • Developer - Branson Group
  • Architect - DKO Architechture 
  • Builder - Viva Building Solutions
  • No. Dwellings - 8

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

October 2018

VIVA Building Solutions have been extremely busy over the last few months, with the bulk excavation works for the basement, retention system, bored piers and capping beam all having now been completed.


 

CV

 

CV - Hawthorn East

  • Developer - Blueprint Projects
  • Architect - Elenberg Fraser
  • Builder - Buxton Construction
  • No. Dwellings - 55 

Project Update

  • Expected Construction Completion: April 2019
  • Expected Settlement: Mid 2019
  • Contact: monique@settlement-solutions.com.au

October 2018

We are excited to announce that CV tower structure was topped out on Tuesday 18 September.


 

Embassy Richmond

 

Embassy - Richmond

  • Developer - Blue Earth Group
  • Architect - CHT Architects
  • Builder - Hamilton Marino Builders
  • No. Dwellings - 289 

Project Update

  • Expected Construction Completion: Early/Mid 2019
  • Expected Settlement: Early/Mid 2019
  • Contact: kim@blueearth.com.au

March 2018

Embassy is progressing on track with programme seeing basement works now complete and the construction of the main structure now commencing.


 

FOUND - CARLTON 

  • Developer - Frasers 
  • Architect - Jackson Clements Burrows and Jackson Architecture
  • Builder - Buildcorp
  • No. Dwellings - 69

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

June 2018

We are pleased to advise that construction of Found Carlton has been progressing well: 

- Basement excavation, piling, capping beam and shotcrete has now been completed


No 1 Logo

 

FV - NO. 1 - Fortitude Valley

  • Developer - Gurner
  • Architect - Elenberg Fraser
  • Builder - ICON Construction
  • No. Dwellings - 261 

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: luke@gurner.com.au

September 2018

ICON has now poured level the slab for level 29, with the final floor for the roof top pool expected to be poured in the first week of November.


 

 

GREENWICH FAIRFIELD - FAIRFIELD

  • Developer - Grocon
  • Architect - Jackson Clements Burrows
  • Builder - Atelier Projects
  • No. Dwellings - 75 Townhouses 

Project Update

  • Expected Construction Completion: November 2018
  • Expected Settlement: December 2018
  • Contact: matthew@settlement-solutions.com.au

September 2018

We are pleased to advised that Bank Valuations will be commencing from 13 Novembr 2018.


HEDGELEY - MALVERN EAST

  • Developer - Little Projects
  • Architect - Adeb Architects with SJB Architects
  • Builder - Hutchinson Builders
  • No. Dwellings - 117 

Project Update

  • Expected Construction Completion: December 2018
  • Expected Settlement: December 2018
  • Contact: settlements@littleprojects.com.au

September 2018

With all external screens removed, the beautiful facade of Hedgeley Malvern East is now fully visible from Waverley and Belgrave Raods.


HOLME - COLLINGWOOD 

  • Developer - Cbus Property
  • Architect - John Wardle Architects
  • Builder - Hacer Group Pty Ltd 
  • No. Dwellings - 154 Apartments

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

September 2018

The past three months have been busy onsite at Holme Apartments with completion of the basement car park and the momentous milestone of the pouring of the ground floor slab.


HUNTER - PRAHRAN

  • Developer - ITUM
  • Architect - BG Architecture
  • Builder - Platcon
  • No. Dwellings - 92 

Project Update

  • Expected Construction Completion: Late April 2019
  • Expected Settlement: Late May 2019
  • Contact: clinhart@360propertygroup.com.au

October 2018

Platinum Construction have been making great progress on the construction of Hunter, Prahran, with the above-ground structure rapidly taking form now that the slower moving basement works have been completed.


 

 

KAIZEN - PRESTON

  • Developer - Branson Group
  • Architect - DKO Architecture
  • Builder - Frater Group
  • No. Dwellings - 16 Townhomes 

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

October 2018

Construction at Kaizen, Preston has been progressing well, with the basement wall construction having now been completed, along with the stormwater pits in the basement.


Mckinnon Place

 

Mckinnon Place - Mckinnon

  • Developer - Citiplan
  • Architect - BG Architecture
  • Builder - Bayside Construct
  • No. Dwellings - 23 

Project Update

  • Expected Construction Completion: Q1 2019
  • Expected Settlement: Q1 2019
  • Contact: settlements@citiplan.com.au

September 2018

Hutchinson Builders have no recommenced works onsite at McKinnon Place.


New Charsfield

 

New Charsfield - Melbourne

  • Developer - EBG Developments
  • Architect - Hecker Guthrie
  • Builder - Hamilton Marino Builders
  • No. Dwellings - 125 

Project Update

  • Expected Construction Completion: Early 2019
  • Expected Settlement: Early 2019
  • Contact: settlements@newcharsfield.com.au

October 2018

We are pleased to advise that construction is progressing well, with the structure of New Charsfield now complete.


 

No 1 Porter Street

No 1 Porter ST - Hawthorn East

  • Developer - Blueprint Projects
  • Architect - Elenberg Fraser
  • Builder - Buxton Construction
  • No. Dwellings - 88 

Project Update

  • Expected Construction Completion: Late 2018
  • Expected Settlement: Late 2018
  • Contact: monique@settlement-solutions.com.au

October 2018 

Construction at No1 Porter is progressing well, with levels up to 9 preparing for defecting.


 

 

ORION - BRAYBROOK 

  • Developer - Stockland 
  • Architect - DKO Architecture 
  • Builder - TBA
  • No. Dwellings - 422 Townhomes 

Project Update

  • Expected Construction Completion: Mid/Late 2019
  • Expected Settlement: From Mid/Late 2019
  • Contact:  townhomesettlements@stockland.com.au

August 2018 

We are pleased to advise that construction at Orion Braybrook is progressing well, with civil works for Stages 1A, 1B and 1C now reaching practical completion.


 

Parkridge - NOosa 

  • Developer - Altum Projects
  • Architect - Blackburne Jackson Design and Sparks Architects
  • Builder - Hutchinson Builders
  • No. Dwellings - 167 Apartments/Townhouses

Project Update

  • Expected Construction Completion: From April 2019
  • Expected Settlement: From Mid 2019
  • Contact:  jgilmore@360propertygroup.com.au 

September 2018 

The development team have compiled a quick time-lapse video to show the construction progress to date. 


PRINCE EDWARD RESIDENCES - McKINNON

  • Developer - Platinum
  • Architect - Taylor Reynolds
  • Builder - Platinum Constructions
  • No. Dwellings - 9

Project Update

  • Expected Construction Completion: Mid-2019
  • Expected Settlement: Mid-2019
  • Contact: clinhart@360propertygroup.com.au

October 2018

Platinum Constructions have been progressing ahead of schedule, with construction of the basement now complete and the ground-level slab to be poured imminently.


 

 

PROSPECT - PASCOE VALE

  • Developer - ID_Land 
  • Architect - Rothelowman
  • Builder - Shape Homes 
  • No. Dwellings - 7

Project Update

  • Expected Construction Completion: 2nd Quarter 2019
  • Expected Settlement: 2nd Quarter 2019 
  • Contact: clinhart@360propertygroup.com.au

October 2018

We are thrilled to advise that civil works at Prospect Pascoe Vale were completed in July and construction of the town homes is now underway.


 

 

 

RIVERONE - FOOTSCRAY

  • Developer - Blue Earth Group
  • Architect - CHT Architects 
  • No. Dwellings - 210 Apartments 

Project Update

  • Expected Construction Completion: Mid 2020
  • Expected Settlement: Mid 2020
  • Contact: kim@blueearth.com.au

August 2018

We are excited to announce that Construction is expected to commence in November 2018.


 

 

RIVERFRONT - FOOTSCRAY

  • Developer - Blue Earth Group
  • Architect - CHT Architects 
  • No. Dwellings - 156 Apartments 

Project Update

  • Expected Construction Completion: Mid 2020
  • Expected Settlement: Mid 2020
  • Contact: kim@blueearth.com.au

August 2018

We are excited to announce that Construction is expected to commence in November 2018.


 

RA

ROSSLYN APARTMENTS - West Melbourne

  • Developer - Starland Pacific
  • Architect - The Buchan Group
  • Builder - LU Simon
  • No. Dwellings - 165 

Project Update

  • Expected Construction Completion: Quarter 2 2019
  • Expected Settlement: Quarter 2 2019
  • Contact: clinhart@360propertygroup.com.au

October 2018

We are pleased to advise that L.U.Simon are making great progress on site with the following milestones having been achieved through Q3 of 2018:


 


The AlexandRA - KEW

  • Developer - Franze Developments
  • Architect - Hecker Guthrie
  • No. Dwellings - 24 Apartments
 

Project Update

  • Expected Construction Completion: September 2018
  • Expected Settlement: September 2018
  • Contact: clinhart@360propertygroup.com.au

October 2017

Construction is now progressing well on The Alexandra after some earlier delays, but excavations and basement works are well underway.


The Grove

 

The Grove - Brunswick West

  • Developer - Blue Earth Group
  • Architect - Map Architects
  • No. Dwellings - 325 across three buildings (Elm 95; Maple 115; Oak 115) 

Project Update

  • Expected Construction Completion: Late 2019
  • Expected Settlement: Late 2019
  • Contact: kim@blueearth.com.au

March 2018

The Grove is progressing ahead of schedule thanks to the hard work of Hamilton Marino who have already completed piling works and are currently in the process of excavation works.


 

 

THE KENT RESIDENCES - HAWTHORN

  • Developer - CDG
  • Architect - Rothelowman
  • Builder - Cobild
  • No. Dwellings - 25 Apartments 

Project Update

  • Expected Construction Completion: Early 2020
  • Expected Settlement: Early 2020
  • Contact: clinhart@360propertygroup.com.au

October 2018

We are thrilled to announce that Cobild have been appointed as the builders who will be working towards deliverying an exceptional development.


 

THE PRINCE - CAULFIELD NORTH

  • Developer - 10 Princes Street Pty Ltd
  • Architect - Taylor Reynolds
  • Builder - Platinum Constructions
  • No. Dwellings - 14 Townhomes

Project Update

  • Expected Construction Completion: Late 2019
  • Expected Settlement: Late 2019
  • Contact: clinhart@360propertygroup.com.au

October 2018

We are pleased to announce that Platinum Constructions have been appointed to build The Prince, Caulfield North.


 

THE WALTER - Hadfield

  • Developer - ID Land
  • Architect - Peddle Thorp
  • Builder - Shape Homes
  • No. Dwellings - 64 Townhouses 

Project Update

  • Expected Construction Completion: Third Quarter 2019
  • Expected Settlement: Third Quarter 2019
  • Contact: clinhart@360propertygroup.com.au

August 2018

Construction at The Walter has been busy over the last few months as civil works have been completed with all internal roads and services installed. Built form is now progressing with the builder, Shape Homes, having commenced Stage 1 townhouses with frames currently being installed.


 

WATERFRONT - FOOTSCRAY

  • Developer - Blue Earth Group
  • Architect - CHT Architects 
  • No. Dwellings - 193 Apartments 

Project Update

  • Expected Construction Completion: Early 2020
  • Expected Settlement: Early 2020
  • Contact: clinhart@360propertygroup.com.au

July 2018

We are excited to announce that construction is expected to commence in September 2018. 


Make an Enquiry

Spinner