Welcome

We are with you every step of the way.

Our sales service does not end once contracts have been signed. We keep our purchasers informed of the development’s progress throughout every stage of the building process.

 

 As we receive construction updates from the developer, we then communicate this information to the purchasers.  It is an exciting process, literally watching your apartment come to life. 

Current Projects

If you are looking for past project updates, please contact:
(03) 9644 2600 or
reception@360propertygroup.com.au

 


 

9 Shuter Street - mOONEE PONDS

  • Developer - CD Group
  • Architect - Jackson Clements Burrows
  • Builder - Balmain & Co
  • No. Dwellings - 61 

Project Update

  • Expected Construction Completion: December 2019
  • Expected Settlement: Early 2020
  • Contact: clinhart@360propertygroup.com.au

May 2018

We are pleased to announce that works have now commenced on site at 9 Shuter Street, Moonee Ponds, with demolition of the existing homes now complete.


 

303 LA TROBE - Melbourne

  • Developer - Figtree
  • Architect - DKO Architecture
  • Builder - TBA
  • No. Dwellings - 215 

Project Update

  • Expected Construction Completion: Late 2020
  • Expected Settlement: Late 2020
  • Contact: info@figtreeasia.com

January 2018

Preparation and pre-commencement activities for construction of 303 La Trobe are well underway, including obtaining final Construction Management and Demolition Permits required for Construction commencement.


388 Lonsdale - Project Logo

 

388 LONSDALE - MELBOURNE

  • Developer - Aurumstone Pty Ltd
  • Architect - Urban Design Architects
  • Builder - Verve Constructions
  • No. Dwellings - 149 Apartments
 

Project Update:

  • Expected Construction Completion: Late 2018
  • Expected Settlement: Late 2018
  • Contact: 388lonsdale@aurumstone.com.au

May 2018

388 Lonsdale has been a hive of activity over the last few months with the main structure now complete up to level 14, with construction of level 15 commencing this week and the façade erected to level 12.


Adelaide St - Project Logo

ADELAIDE ST - MCKINNON

  • Developer - Citiplan
  • Architect - CBG Architecture
  • Builder - Hutchinson Builders
  • No. Dwellings - 34 Townhouses
 

Project Update:

  • Expected Construction Completion: December 2018
  • Expected Settlement: Late 2018
  • Contact: settlements@citiplan.com.au

June 2018

The structural steel and wall framing erection is nearing completion across the development. Where the framing is finished, work has commenced on the roofing and cladding and window installation


 

 

ALBERT PLACE RESIDENCES - MELBOURNE

  • Developer - Gurner
  • Architect - Elenberg Fraser
  • Builder - Crema Constructions
  • No. Dwellings - 153 Apartments
 

Project Update

  • Expected Construction Completion: Early 2020 
  • Expected Settlement: Early 2020
  • Contact: jessica@gurner.com.au

August 2018

We are pleased to advise that Crema Constructions are continuing bulk excavation works.


 

ATHERTON TCE - GLEN IRIS

  • Developer - Citiplan
  • Architect - BG Architects
  • Builder - Hutchinson Builders
  • No. Dwellings - 11 townhomes 
 

Project Update

  • Expected Construction Completion: May 2019
  • Expected Settlement: June 2019
  • Contact: clinhart@360propertygroup.com.au

August 2018

Construction on site ar Atherton Terrace, Glen Iris is progressing well with the agove-ground structure now taking form.


 

BOAT HOUSE - FOOTSCRAY

  • Developer - Blue Earth Group
  • Architect - CHT Architects
  • Builder - Hamilton Marino
  • No. Dwellings - 193 

Project Update

  • Expected Construction Completion: Late 2019
  • Expected Settlement: Late 2019
  • Contact: kim@blueearth.com.au

July 2018

Boat House, Footscray continues to progress on programme thanks to the hard work of Hamilton Marino Builders.


Brightwood Monash - Logo

 

Brightwood Monash - Clayton

  • Developer - NX Property
  • Architect - Mushan Projects
  • Builder - Valeo
  • No. Dwellings - 129 Apartments and 26 Townhomes 

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

January 2018

Preparation activities for construction of Brightwood Monash are well underway with demolition works now complete.


 

Cascades residences - Clyde north

  • Developer - Villa World
  • Architect - Villa World 
  • No. Dwellings - 29 Townhouses 

Project Update

  • Expected Construction Completion: From September 2018
  • Expected Settlement: From Mid/Late September 2018
  • Contact: acreighton@villaworld.com.au

June 2018

We are pleased to advise that works are progressing quickly on site at Cascades Residences with lots 1 & 2  are ready for defecting by the Villa World team. lots 3 to 10 have all kitchens and stone tops fitted with tiling and internal painting taking place. Lot 11 to 13 are ready for fix out


Casey Green

 

Casey Green - Narre Warren

  • Developer - Osanrae
  • Architect - Demaine
  • Builder - Yarra Bank Homes and Marcus Group
  • No. Dwellings - 58 

Project Update

  • Expected Construction Completion: 3rd Quarter 18 - 1st Quarter 19
  • Expected Settlement: 4th Quarter 18 - 2nd Quarter 19
  • Contact: myeoh@osanrae.com.au

June 2018

We are happy to report that builders have been appointed and construction has commenced for Stages 1 and 2 at Casey Green.


 

 

 

CITRINE - ESSENDON

  • Developer - Branson Group
  • Architect - DKO Architechture 
  • Builder - Viva Building Solutions
  • No. Dwellings - 8

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

August 2018

Construction at Citrine Essendon is well underway with the permanent power pit and piling having been completed.


 

CV

 

CV - Hawthorn East

  • Developer - Blueprint Projects
  • Architect - Elenberg Fraser
  • Builder - Buxton Construction
  • No. Dwellings - 55 

Project Update

  • Expected Construction Completion: April 2019
  • Expected Settlement: Mid 2019
  • Contact: monique@settlement-solutions.com.au

September 2018

Construction on CV Tower is progressing well, with Buxton Construction aiming to top out over the coming weeks.


 

Embassy Richmond

 

Embassy - Richmond

  • Developer - Blue Earth Group
  • Architect - CHT Architects
  • Builder - Hamilton Marino Builders
  • No. Dwellings - 289 

Project Update

  • Expected Construction Completion: Early/Mid 2019
  • Expected Settlement: Early/Mid 2019
  • Contact: kim@blueearth.com.au

March 2018

Embassy is progressing on track with programme seeing basement works now complete and the construction of the main structure now commencing.


 

FOUND - CARLTON 

  • Developer - Frasers 
  • Architect - Jackson Clements Burrows and Jackson Architecture
  • Builder - Buildcorp
  • No. Dwellings - 69

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

June 2018

We are pleased to advise that construction of Found Carlton has been progressing well: 

- Basement excavation, piling, capping beam and shotcrete has now been completed


No 1 Logo

 

FV - NO. 1 - Fortitude Valley

  • Developer - Gurner
  • Architect - Elenberg Fraser
  • Builder - ICON Construction
  • No. Dwellings - 261 

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: jessica@gurner.com.au

August 2018

ICON Construction continue to progress through the pouring of the floors with floors now complete to level 23 with the lisft cores complete upto level 27. 


 

 

GREENWICH FAIRFIELD - FAIRFIELD

  • Developer - Grocon
  • Architect - Jackson Clements Burrows
  • Builder - Atelier Projects
  • No. Dwellings - 75 Townhouses 

Project Update

  • Expected Construction Completion: 4th Quarter 2018
  • Expected Settlement: 4th Quarter 2018
  • Contact: matthew@settlement-solutions.com.au

September 2018

- Scaffolding has now been removed

- Plastering inside the apartments is almost complete


HEDGELEY - MALVERN EAST

  • Developer - Little Projects
  • Architect - Adeb Architects with SJB Architects
  • Builder - Hutchinson Builders
  • No. Dwellings - 117 

Project Update

  • Expected Construction Completion: December 2018
  • Expected Settlement: December 2018
  • Contact: settlements@littleprojects.com.au

August 2018

We're excited to announce that the creane at Hedgeley Malber East will soon be removed, and the external screens on the facade are in the process of being taken down from Waverley and Belgrave Roads.


HOLME - COLLINGWOOD 

  • Developer - Cbus Property
  • Architect - John Wardle Architects
  • Builder - Hacer Group Pty Ltd 
  • No. Dwellings - 154 Apartments

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

April 2018

Head contractor Hacer continue to impress on site with the site retention now fully completed and excavation works well advanced.


HUNTER - PRAHRAN

  • Developer - ITUM
  • Architect - BG Architecture
  • Builder - Platcon
  • No. Dwellings - 92 

Project Update

  • Expected Construction Completion: Late April 2019
  • Expected Settlement: Late May 2019
  • Contact: clinhart@360propertygroup.com.au

February 2018

Basement retention piling around the perimeter of the basement is complete and capping beams are in progress. Bulk excavation of soil to reveal the basement has also now been completed.


 

 

KAIZEN - PRESTON

  • Developer - Branson Group
  • Architect - DKO Architecture
  • Builder - Frater Group
  • No. Dwellings - 16 Townhomes 

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

August 2018

It has been a very busy month at Kaizen Preston, with the bulk excavation work for the basement having now been completed. 


Mckinnon Place

 

Mckinnon Place - Mckinnon

  • Developer - Citiplan
  • Architect - BG Architecture
  • Builder - Bayside Construct
  • No. Dwellings - 23 

Project Update

  • Expected Construction Completion: Late November 2018
  • Expected Settlement: Late 2018
  • Contact: settlements@citiplan.com.au

July 2018

Citiplan are pleased to advise that Hutchinson Builders have been appointed to complete the outstanding construction works at McKinnon Place.


New Charsfield

 

New Charsfield - Melbourne

  • Developer - EBG Developments
  • Architect - Hecker Guthrie
  • Builder - Hamilton Marino Builders
  • No. Dwellings - 125 

Project Update

  • Expected Construction Completion: Early 2019
  • Expected Settlement: Early 2019
  • Contact: settlements@newcharsfield.com.au

July 2018

New Charsfield has been a hub of activity over the last few months with lifecore now reaching new heights up to level 12-13.


 

No 1 Porter Street

No 1 Porter ST - Hawthorn East

  • Developer - Blueprint Projects
  • Architect - Elenberg Fraser
  • Builder - Buxton Construction
  • No. Dwellings - 88 

Project Update

  • Expected Construction Completion: Late 2018
  • Expected Settlement: Late 2018
  • Contact: monique@settlement-solutions.com.au

August 2018 

Buxton Construction is progressing well with the final completion of the structure for all levels to be completed in the coming week.


 

 

ORION - BRAYBROOK 

  • Developer - Stockland 
  • Architect - DKO Architecture 
  • Builder - TBA
  • No. Dwellings - 422 Townhomes 

Project Update

  • Expected Construction Completion: Mid/Late 2019
  • Expected Settlement: From Mid/Late 2019
  • Contact:  townhomesettlements@stockland.com.au

August 2018 

We are pleased to advise that construction at Orion Braybrook is progressing well, with civil works for Stages 1A, 1B and 1C now reaching practical completion.


 

Parkridge - NOosa 

  • Developer - Altum Projects
  • Architect - Blackburne Jackson Design and Sparks Architects
  • Builder - Hutchinson Builders
  • No. Dwellings - 167 Apartments/Townhouses

Project Update

  • Expected Construction Completion: From April 2019
  • Expected Settlement: From Mid 2019
  • Contact:  jgilmore@360propertygroup.com.au 

September 2018 

The development team have compiled a quick time-lapse video to show the construction progress to date. 


PRINCE EDWARD RESIDENCES - McKINNON

  • Developer - Platinum
  • Architect - Taylor Reynolds
  • Builder - Platinum Constructions
  • No. Dwellings - 9

Project Update

  • Expected Construction Completion:Mid-2019
  • Expected Settlement:Mid-2019
  • Contact: clinhart@360propertygroup.com.au

July 2018

We are excited to announce that Platinum Constructions have been appointed to build Prince Edward Residences. Onsite, the existing dwellings have now been demolished.


 

 

PROSPECT - PASCOE VALE

  • Developer - ID_Land 
  • Architect - Rothelowman
  • Builder - Shape Homes 
  • No. Dwellings - 7

Project Update

  • Expected Construction Completion: 2nd Quarter 2019
  • Expected Settlement: 2nd Quarter 2019 
  • Contact: clinhart@360propertygroup.com.au

March 2018

We are excited to announce that civil works have commenced on site for Prospect, with sewer works well underway to prepare for Shape Homes to commence construction works on the development. 


 

 

 

RIVERONE - FOOTSCRAY

  • Developer - Blue Earth Group
  • Architect - CHT Architects 
  • No. Dwellings - 210 Apartments 

Project Update

  • Expected Construction Completion: Mid 2020
  • Expected Settlement: Mid 2020
  • Contact: kim@blueearth.com.au

August 2018

We are excited to announce that Construction is expected to commence in November 2018.


 

 

RIVERFRONT - FOOTSCRAY

  • Developer - Blue Earth Group
  • Architect - CHT Architects 
  • No. Dwellings - 156 Apartments 

Project Update

  • Expected Construction Completion: Mid 2020
  • Expected Settlement: Mid 2020
  • Contact: kim@blueearth.com.au

August 2018

We are excited to announce that Construction is expected to commence in November 2018.


 

RA

ROSSLYN APARTMENTS - West Melbourne

  • Developer - Starland Pacific
  • Architect - The Buchan Group
  • Builder - LU Simon
  • No. Dwellings - 165 

Project Update

  • Expected Construction Completion: Quarter 2 2019
  • Expected Settlement: Quarter 2 2019
  • Contact: clinhart@360propertygroup.com.au

June 2018

We are pleased to advise that L.U.Simon are making great progress on site with the following milestones having been achieved through Q2 of 2018:


 


The AlexandRA - KEW

  • Developer - Franze Developments
  • Architect - Hecker Guthrie
  • No. Dwellings - 24 Apartments
 

Project Update

  • Expected Construction Completion: September 2018
  • Expected Settlement: September 2018
  • Contact: clinhart@360propertygroup.com.au

October 2017

Construction is now progressing well on The Alexandra after some earlier delays, but excavations and basement works are well underway.


The Grove

 

The Grove - Brunswick West

  • Developer - Blue Earth Group
  • Architect - Map Architects
  • No. Dwellings - 325 across three buildings (Elm 95; Maple 115; Oak 115) 

Project Update

  • Expected Construction Completion: Late 2019
  • Expected Settlement: Late 2019
  • Contact: kim@blueearth.com.au

March 2018

The Grove is progressing ahead of schedule thanks to the hard work of Hamilton Marino who have already completed piling works and are currently in the process of excavation works.


 

THE WALTER - Hadfield

  • Developer - ID Land
  • Architect - Peddle Thorp
  • Builder - Shape Homes
  • No. Dwellings - 64 Townhouses 

Project Update

  • Expected Construction Completion: Third Quarter 2019
  • Expected Settlement: Third Quarter 2019
  • Contact: clinhart@360propertygroup.com.au

August 2018

Construction at The Walter has been busy over the last few months as civil works have been completed with all internal roads and services installed. Built form is now progressing with the builder, Shape Homes, having commenced Stage 1 townhouses with frames currently being installed.


 

WATERFRONT - FOOTSCRAY

  • Developer - Blue Earth Group
  • Architect - CHT Architects 
  • No. Dwellings - 193 Apartments 

Project Update

  • Expected Construction Completion: Early 2020
  • Expected Settlement: Early 2020
  • Contact: clinhart@360propertygroup.com.au

July 2018

We are excited to announce that construction is expected to commence in September 2018. 


Make an Enquiry

Spinner