Welcome

We are with you every step of the way.

Our sales service does not end once contracts have been signed. We keep our purchasers informed of the development’s progress throughout every stage of the building process.

 

 As we receive construction updates from the developer, we then communicate this information to the purchasers.  It is an exciting process, literally watching your apartment come to life. 

We would like to introduce Three Sixty° Property Group property management, a specialist division within Three Sixty° Property Group.

We specialise in off the plan leasing of brand new apartments in and across the city of Melbourne. Our full attention is solely focused on our landlords and tenants, as your investment is our priority.

 

Enquire Today

Current Projects

If you are looking for past project updates, please contact:
(03) 9644 2600 or
reception@360propertygroup.com.au

 


 

9 Shuter Street - mOONEE PONDS

  • Developer - CD Group
  • Architect - Jackson Clements Burrows
  • Builder - Balmain & Co
  • No. Dwellings - 61 

Project Update

  • Expected Construction Completion: September 2019
  • Expected Settlement: November 2019
  • Contact: clinhart@360propertygroup.com.au

February 2018

We are pleased to announce that Balmain & Co have been awarded the build contract for 9 Shuter Street.


 

303 LA TROBE - Melbourne

  • Developer - Figtree
  • Architect - DKO Architecture
  • Builder - TBA
  • No. Dwellings - 215 

Project Update

  • Expected Construction Completion: Late 2020
  • Expected Settlement: Late 2020
  • Contact: info@figtreeasia.com

January 2018

Preparation and pre-commencement activities for construction of 303 La Trobe are well underway, including obtaining final Construction Management and Demolition Permits required for Construction commencement.


388 Lonsdale - Project Logo

 

388 LONSDALE - MELBOURNE

  • Developer - Aurumstone Pty Ltd
  • Architect - Urban Design Architects
  • Builder - Verve Constructions
  • No. Dwellings - 149 Apartments
 

Project Update:

  • Expected Construction Completion: Late 2018
  • Expected Settlement: Late 2018
  • Contact: 388lonsdale@aurumstone.com.au

May 2018

388 Lonsdale has been a hive of activity over the last few months with the main structure now complete up to level 14, with construction of level 15 commencing this week and the façade erected to level 12.


Adelaide St - Project Logo

ADELAIDE ST - MCKINNON

  • Developer - Citiplan
  • Architect - CBG Architecture
  • Builder - Hutchinson Builders
  • No. Dwellings - 34 Townhouses
 

Project Update:

  • Expected Construction Completion: December 2018
  • Expected Settlement: TBA
  • Contact: clinhart@360propertygroup.com.au

 March 2018

The basement structure is now complete and structural steel to townhouses as well as wall framing have commenced erection.


 

 

ALBERT PLACE RESIDENCES - MELBOURNE

  • Developer - Gurner
  • Architect - Elenberg Fraser
  • Builder - Crema Constructions
  • No. Dwellings - 153 Apartments
 

Project Update

  • Expected Construction Completion: Early 2020 
  • Expected Settlement: 2020
  • Contact: jessica@gurner.com.au

April 2018

Progress of the Albert Place REsidence basement continues, with Crema Constructions having completed the D-Wall excavation and concrete pour along Bowen Crescent.


 

ATHERTON TCE - GLEN IRIS

  • Developer - Citiplan
  • Architect - BG Architects
  • Builder - Hutchinson Builders
  • No. Dwellings - 11 townhomes 
 

Project Update

  • Expected Construction Completion: May 2019
  • Expected Settlement: June 2019
  • Contact: clinhart@360propertygroup.com.au

April 2018

We are thrilled to announce that demolition of the previously existing site is now fully complete.


Avant

 

AVANT - MELBOURNE

  • Developer - World Class Global
  • Architect - Elenberg Fraser
  • Builder - Probuild
  • No. Dwellings - 456 

Project Update

  • Expected Construction Completion: Stage 1: February 2018 / Stage 2: August 2018
  • Expected Settlement: Stage 1: 9th March 2018 / Stage 2: August 2018
  • Contact: avant@wcg.com.sg

May 2018

We are pleased to announce that settlements for Stage 1 Avant have now taken place. Construction is continuing to progress well with the structure now complete and final fitout of the apartments progressing up to level 54 over the coming weeks.


 

BOAT HOUSE - FOOTSCRAY

  • Developer - Blue Earth Group
  • Architect - CHT Architects
  • Builder - Hamilton Marino
  • No. Dwellings - 193 

Project Update

  • Expected Construction Completion: Mid/Late 2019
  • Expected Settlement: Mid/Late 2019
  • Contact: kim@blueearth.com.au

May 2018

We are pleased to announce that Hamilton Marino Builders have been appointed to build Boat House,Footscray.


Brightwood Monash - Logo

 

Brightwood Monash - Clayton

  • Developer - NX Property
  • Architect - Mushan Projects
  • Builder - Valeo
  • No. Dwellings - 129 Apartments and 26 Townhomes 

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

January 2018

Preparation activities for construction of Brightwood Monash are well underway with demolition works now complete.


Casa Del Mar

CASA DEL MAR - MORDIALLOC

  • Developer - Kokoda
  • Architect - Chamberlin Architects
  • Builder - Creation Homes
  • No. Dwellings - 68 Townhouses 

Project Update

  • Expected Construction Completion: Final Stage - April 2018
  • Expected Settlement: From December 2017
  • Contact: monique@settlement-solutions.com.au

May 2018

We are pleased to advise that Stage 4A (Lots 1 to 7 & 59 to 66) has bee called for bank valuations to commence from Monday, 21 May.


 

Cascades residences - Clyde north

  • Developer - Villa World
  • Architect - Villa World 
  • No. Dwellings - 29 Townhouses 

Project Update

  • Expected Construction Completion: Stage 1: 3rd Quarter 18, Stage 2: 4th Quarter 18
  • Expected Settlement: Stage 1: 3rd Quarter 18, Stage 2: 4th Quarter 18
  • Contact: clinhart@360propertygroup.com.au

April 2018

We are pleased to advise that the slab has been poured for most lots and framework has been erected from lots 1-10.


Casey Green

 

Casey Green - Narre Warren

  • Developer - Osanrae
  • Architect - Demaine
  • Builder - Yarra Bank Homes and Marcus Group
  • No. Dwellings - 58 

Project Update

  • Expected Construction Completion: 3rd Quarter 18 - 1st Quarter 19
  • Expected Settlement: 4th Quarter 18 - 2nd Quarter 19
  • Contact: myeoh@osanrae.com.au

March 2018

We are happy to report that builders have been appointed and construction has commenced for Stages 1 and 2 at Casey Green.


 

CV

 

CV - Hawthorn East

  • Developer - Blueprint Projects
  • Architect - Elenberg Fraser
  • Builder - Buxton Construction
  • No. Dwellings - 55 

Project Update

  • Expected Construction Completion: Early 2019
  • Expected Settlement: TBA
  • Contact: clinhart@360propertygroup.com.au

March 2018

CV Tower's slabs are now being poured up until level 1, with some areas now poured up until level 2. 


 

Dux

 

DUX - RICHMOND

  • Developer - Little Projects
  • Architect - Rothe Lowman
  • Builder - Hacer
  • No. Dwellings - 175 

Project Update

  • Expected Construction Completion: May 2018
  • Expected Settlement: Mid-May 2018
  • Contact: settlements@littleprojects.com.au

May 2018

We are pleased to advise that Occupancy Permit and Title Registration requirements have been met with settlement due to take place mid-May 2018.


 

Embassy Richmond

 

Embassy - Richmond

  • Developer - Blue Earth Group
  • Architect - CHT Architects
  • Builder - Hamilton Marino Builders
  • No. Dwellings - 289 

Project Update

  • Expected Construction Completion: Early 2019
  • Expected Settlement: Early 2019
  • Contact: kim@blueearth.com.au

March 2018

Constructionis progressing ahead of schedule with the piling now complete and excavation works well underway. 


 

FOUND - CARLTON 

  • Developer - Frasers 
  • Architect - Jackson Clements Burrows and Jackson Architecture
  • Builder - Buildcorp
  • No. Dwellings - 69

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

March 2018

We are pleased to advise that construction of Found Carlton has commenced and are underway on construction of the basement.


No 1 Logo

 

FV - NO. 1 - Fortitude Valley

  • Developer - Gurner
  • Architect - Elenberg Fraser
  • Builder - ICON Construction
  • No. Dwellings - 261 

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: jessica@gurner.com.au

April 2018

ICON Construction has been progressing efficiently as the weather imporves and the typical floor building cycle has been established.


 

 

GREENWICH FAIRFIELD - FAIRFIELD

  • Developer - Grocon
  • Architect - Jackson Clements Burrows
  • Builder - Atelier Projects
  • No. Dwellings - 75 Townhouses 

Project Update

  • Expected Construction Completion: August 2018
  • Expected Settlement: 3rd Quarter 2018
  • Contact: matthew@settlement-solutions.com.au

February 2018

Greenwich Fairfield is seeing exciting activity with the concrete structure of the building being the focus on site.


HEDGELEY - MALVERN EAST

  • Developer - Little Projects
  • Architect - Adeb Architects with SJB Architects
  • Builder - Hutchinson Builders
  • No. Dwellings - 117 

Project Update

  • Expected Construction Completion: Late 2018
  • Expected Settlement: Late 2018
  • Contact: settlements@littleprojects.com.au

March 2018

Hedgeley Malvern East is beginning to take shape with the slab for the atrium garden level now complete.


HOLME - COLLINGWOOD 

  • Developer - Cbus Property
  • Architect - John Wardle Architects
  • Builder - Hacer Group Pty Ltd 
  • No. Dwellings - 154 Apartments

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

April 2018

Head contractor Hacer continue to impress on site with the site retention now fully completed and excavation works well advanced.


HUNTER - PRAHRAN

  • Developer - ITUM
  • Architect - BG Architecture
  • Builder - Platcon
  • No. Dwellings - 92 

Project Update

  • Expected Construction Completion: April 2019
  • Expected Settlement: TBA
  • Contact: clinhart@360propertygroup.com.au

February 2018

Basement retention piling around the perimeter of the basement is complete and capping beams are in progress. Bulk excavation of soil to reveal the basement has commenced.


Mckinnon Place

 

Mckinnon Place - Mckinnon

  • Developer - Citiplan
  • Architect - BG Architecture
  • Builder - Bayside Construct
  • No. Dwellings - 23 

Project Update

  • Expected Construction Completion: July 2018
  • Expected Settlement: August 2018
  • Contact: settlements@citiplan.com.au

April 2018

Bayside Construct have continued to make good progress on site with the following works having now been completed:

    • Roof Complete
    • Facade Cladding 80% Complete
    • Internal Staircases Installed
    • Internal Tiling Underway

New Charsfield

 

New Charsfield - Melbourne

  • Developer - EBG Developments
  • Architect - Hecker Guthrie
  • Builder - Hamilton Marino Builders
  • No. Dwellings - 125 

Project Update

  • Expected Construction Completion: Early 2019
  • Expected Settlement: Late January to February 2019
  • Contact: clinhart@360propertygroup.com.au

May 2018

New Charsfield has been a hub of activity over the last few months with lifecore now reaching new heights up to level 12-13.


 

No 1 Porter Street

No 1 Porter ST - Hawthorn East

  • Developer - Blueprint Projects
  • Architect - Elenberg Fraser
  • Builder - Buxton Construction
  • No. Dwellings - 88 

Project Update

  • Expected Construction Completion: Late 2018
  • Expected Settlement: Late 2018
  • Contact: clinhart@360propertygroup.com.au

March 2018 

The building's structure has now been completed up to level 11.


 

 

ORION - BRAYBROOK 

  • Developer - Stockland 
  • Architect - DKO Architecture 
  • Builder - TBA
  • No. Dwellings - 422 Townhomes 

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact:  townhomesettlements@stockland.com.au

March 2018 

We are pleased to advise that construction at Orion Braybrook is progressing well, with civil works underway for Stage 1.


 

 

PROSPECT - PASCOE VALE

  • Developer - ID_Land 
  • Architect - Rothelowman
  • Builder - Shape Homes 
  • No. Dwellings - 7

Project Update

  • Expected Construction Completion: 2nd Quarter 2019
  • Expected Settlement: 2nd Quarter 2019 
  • Contact: clinhart@360propertygroup.com.au

March 2018

We are excited to announce that civil works have commenced on site for Prospect, with sewer works well underway to prepare for Shape Homes to commence construction works on the development. 


 

QA

 

QueenS AVENUE - Hawthorn

  • Developer - Urban
  • Architect - CHT Architects
  • Builder - Orange Building Solutions
  • No. Dwellings - 72 

Project Update

  • Expected Construction Completion: May 2018
  • Expected Settlement: June 2018
  • Contact: clinhart@360propertygroup.com.au

March 2018

We are pleased to advise that Queens Avenue Hawthorn is now complete with Bank Valuations currently taken place on site.


 

RA

ROSSLYN APARTMENTS - West Melbourne

  • Developer - Starland Pacific
  • Architect - The Buchan Group
  • Builder - LU Simon
  • No. Dwellings - 165 

Project Update

  • Expected Construction Completion: Early 2019
  • Expected Settlement: Early 2019
  • Contact: clinhart@360propertygroup.com.au

March 2018

We are pleased to advise that excavation works are almost complete on site. 


 


The AlexandRA - KEW

  • Developer - Franze Developments
  • Architect - Hecker Guthrie
  • No. Dwellings - 24 Apartments
 

Project Update

  • Expected Construction Completion: September 2018
  • Expected Settlement: September 2018
  • Contact: clinhart@360propertygroup.com.au

October 2017

Construction is now progressing well on The Alexandra after some earlier delays, but excavations and basement works are well underway.


The Grove

 

The Grove - Brunswick West

  • Developer - Blue Earth Group
  • Architect - Map Architects
  • No. Dwellings - 325 across three buildings (Elm 95; Maple 115; Oak 115) 

Project Update

  • Expected Construction Completion: Late 2019
  • Expected Settlement: Late 2019
  • Contact: kim@blueearth.com.au

March 2018

The Grove is progressing ahead of schedule thanks to the hard work of Hamilton Marino who have already completed piling works and are currently in the process of excavation works.


 

The Grove ON JASPER - BENTLEIGH 

  • Developer - JW Land Development
  • Architect - Front Studio
  • Builder - Chase Building Group
  • No. Dwellings - 24 Apartments 
 

Project Update

  • Expected Construction Completion: April 2018
  • Expected Settlement: May 2018
  • Contact: clinhart@360propertygroup.com.au

March 2018

We are pleased to announce that construction is progressing and is estimated to be completed in April.


The International

The International - Melbourne

  • Developer - Blue Earth Group
  • Architect - CHT Architects
  • No. Dwellings - 168

Project Update

  • Expected Construction Completion: Mid 2018
  • Expected Settlement: Mid June 2018
  • Contact: kim@blueearth.com.au

March 2018

We are pleased to advise that construction at The International is almost complete and ready for bank valuation bookings.


 

THE WALTER - Hadfield

  • Developer - ID Land
  • Architect - Peddle Thorp
  • Builder - Shape Homes
  • No. Dwellings - 64 Townhouses 

Project Update

  • Expected Construction Completion: Third Quarter 2019
  • Expected Settlement: Third Quarter 2019
  • Contact: clinhart@360propertygroup.com.au

May 2018

The Walter has been a hive of activity over the last few months with civil works progressing well. With services now installed and kerb starting to be poured, the developer is expecting that civil will be completed in early June. Thereafter, the builder, Shape Homes, are expected to commence on site.


United Richmond

 

United Richmond - Richmond

  • Developer - Blue Earth Group
  • Architect - CHT Architects
  • Builder - Hamilton Marino Builders
  • No. Dwellings - 112 Apartments 

Project Update

  • Expected Construction Completion: Mid 2018
  • Expected Settlement: Mid June 2018
  • Contact: kim@blueearth.com.au

March 2018

We are pleased to advise that construction at The International is almost complete and ready for bank valuation bookings.


Make an Enquiry

Spinner