Welcome

We are with you every step of the way.

Our sales service does not end once contracts have been signed. We keep our purchasers informed of the development’s progress throughout every stage of the building process.

 

 As we receive construction updates from the developer, we then communicate this information to the purchasers.  It is an exciting process, literally watching your apartment come to life. 

We would like to introduce Three Sixty° Property Group property management, a specialist division within Three Sixty° Property Group.

We specialise in off the plan leasing of brand new apartments in and across the city of Melbourne. Our full attention is solely focused on our landlords and tenants, as your investment is our priority.

 

Enquire Today

Current Projects

If you are looking for past project updates, please contact:
(03) 9644 2600 or
reception@360propertygroup.com.au

 


 

9 Shuter Street - mOONEE PONDS

  • Developer - CD Group
  • Architect - Jackson Clements Burrows
  • Builder - Balmain & Co
  • No. Dwellings - 61 

Project Update

  • Expected Construction Completion: December 2019
  • Expected Settlement: Early 2020
  • Contact: clinhart@360propertygroup.com.au

May 2018

We are pleased to announce that works have now commenced on site at 9 Shuter Street, Moonee Ponds, with demolition of the existing homes now complete.


 

303 LA TROBE - Melbourne

  • Developer - Figtree
  • Architect - DKO Architecture
  • Builder - TBA
  • No. Dwellings - 215 

Project Update

  • Expected Construction Completion: Late 2020
  • Expected Settlement: Late 2020
  • Contact: info@figtreeasia.com

January 2018

Preparation and pre-commencement activities for construction of 303 La Trobe are well underway, including obtaining final Construction Management and Demolition Permits required for Construction commencement.


388 Lonsdale - Project Logo

 

388 LONSDALE - MELBOURNE

  • Developer - Aurumstone Pty Ltd
  • Architect - Urban Design Architects
  • Builder - Verve Constructions
  • No. Dwellings - 149 Apartments
 

Project Update:

  • Expected Construction Completion: Late 2018
  • Expected Settlement: Late 2018
  • Contact: 388lonsdale@aurumstone.com.au

May 2018

388 Lonsdale has been a hive of activity over the last few months with the main structure now complete up to level 14, with construction of level 15 commencing this week and the façade erected to level 12.


Adelaide St - Project Logo

ADELAIDE ST - MCKINNON

  • Developer - Citiplan
  • Architect - CBG Architecture
  • Builder - Hutchinson Builders
  • No. Dwellings - 34 Townhouses
 

Project Update:

  • Expected Construction Completion: December 2018
  • Expected Settlement: Late 2018
  • Contact: settlements@citiplan.com.au

June 2018

The structural steel and wall framing erection is nearing completion across the development. Where the framing is finished, work has commenced on the roofing and cladding and window installation


 

 

ALBERT PLACE RESIDENCES - MELBOURNE

  • Developer - Gurner
  • Architect - Elenberg Fraser
  • Builder - Crema Constructions
  • No. Dwellings - 153 Apartments
 

Project Update

  • Expected Construction Completion: Early 2020 
  • Expected Settlement: Early 2020
  • Contact: jessica@gurner.com.au

June 2018

We are pleased to advise that Crema Constructions has completed all segments of the Albert Place basement diaphragm, with bulk excavation to commence the first week of July 2018.


 

ATHERTON TCE - GLEN IRIS

  • Developer - Citiplan
  • Architect - BG Architects
  • Builder - Hutchinson Builders
  • No. Dwellings - 11 townhomes 
 

Project Update

  • Expected Construction Completion: May 2019
  • Expected Settlement: June 2019
  • Contact: clinhart@360propertygroup.com.au

April 2018

We are thrilled to announce that demolition of the previously existing site is now fully complete.


Avant

 

AVANT - MELBOURNE

  • Developer - World Class Global
  • Architect - Elenberg Fraser
  • Builder - Probuild
  • No. Dwellings - 456 

Project Update

  • Expected Construction Completion: Stage 1: February 2018 / Stage 2: August 2018
  • Expected Settlement: Stage 1: 9th March 2018 / Stage 2: August 2018
  • Contact: avant@wcg.com.sg

May 2018

We are pleased to announce that settlements for Stage 1 Avant have now taken place. Construction is continuing to progress well with the structure now complete and final fitout of the apartments progressing up to level 54 over the coming weeks.


 

BOAT HOUSE - FOOTSCRAY

  • Developer - Blue Earth Group
  • Architect - CHT Architects
  • Builder - Hamilton Marino
  • No. Dwellings - 193 

Project Update

  • Expected Construction Completion: Late 2019
  • Expected Settlement: Late 2019
  • Contact: kim@blueearth.com.au

July 2018

Boat House, Footscray continues to progress on programme thanks to the hard work of Hamilton Marino Builders.


Brightwood Monash - Logo

 

Brightwood Monash - Clayton

  • Developer - NX Property
  • Architect - Mushan Projects
  • Builder - Valeo
  • No. Dwellings - 129 Apartments and 26 Townhomes 

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

January 2018

Preparation activities for construction of Brightwood Monash are well underway with demolition works now complete.


Casa Del Mar

CASA DEL MAR - MORDIALLOC

  • Developer - Kokoda
  • Architect - Chamberlin Architects
  • Builder - Creation Homes
  • No. Dwellings - 68 Townhouses 

Project Update

  • Expected Construction Completion: June 2018
  • Expected Settlement: From December 2017
  • Contact: monique@settlement-solutions.com.au

May 2018

We are pleased to advise that Stage 3B (Lots 53A to 58) have been called for settlement which will commence from Wednesday, 27 June.


 

Cascades residences - Clyde north

  • Developer - Villa World
  • Architect - Villa World 
  • No. Dwellings - 29 Townhouses 

Project Update

  • Expected Construction Completion: From September 2018
  • Expected Settlement: From Mid/Late September 2018
  • Contact: acreighton@villaworld.com.au

June 2018

We are pleased to advise that works are progressing quickly on site at Cascades Residences with lots 1 & 2  are ready for defecting by the Villa World team. lots 3 to 10 have all kitchens and stone tops fitted with tiling and internal painting taking place. Lot 11 to 13 are ready for fix out


Casey Green

 

Casey Green - Narre Warren

  • Developer - Osanrae
  • Architect - Demaine
  • Builder - Yarra Bank Homes and Marcus Group
  • No. Dwellings - 58 

Project Update

  • Expected Construction Completion: 3rd Quarter 18 - 1st Quarter 19
  • Expected Settlement: 4th Quarter 18 - 2nd Quarter 19
  • Contact: myeoh@osanrae.com.au

June 2018

We are happy to report that builders have been appointed and construction has commenced for Stages 1 and 2 at Casey Green.


 

CV

 

CV - Hawthorn East

  • Developer - Blueprint Projects
  • Architect - Elenberg Fraser
  • Builder - Buxton Construction
  • No. Dwellings - 55 

Project Update

  • Expected Construction Completion: April/May2019
  • Expected Settlement: Mid 2019
  • Contact: monique@settlement-solutions.com.au

June 2018

The construction is progressing well with the residential floors well underway. The office levels and level 5 have also been constructed.


 

Embassy Richmond

 

Embassy - Richmond

  • Developer - Blue Earth Group
  • Architect - CHT Architects
  • Builder - Hamilton Marino Builders
  • No. Dwellings - 289 

Project Update

  • Expected Construction Completion: Early/Mid 2019
  • Expected Settlement: Early/Mid 2019
  • Contact: kim@blueearth.com.au

March 2018

Embassy is progressing on track with programme seeing basement works now complete and the construction of the main structure now commencing.


 

FOUND - CARLTON 

  • Developer - Frasers 
  • Architect - Jackson Clements Burrows and Jackson Architecture
  • Builder - Buildcorp
  • No. Dwellings - 69

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

June 2018

We are pleased to advise that construction of Found Carlton has been progressing well: 

- Basement excavation, piling, capping beam and shotcrete has now been completed


No 1 Logo

 

FV - NO. 1 - Fortitude Valley

  • Developer - Gurner
  • Architect - Elenberg Fraser
  • Builder - ICON Construction
  • No. Dwellings - 261 

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: jessica@gurner.com.au

June 2018

ICON Construction continue to progress through the pouring of the floors with floors now complete to level 16.


 

 

GREENWICH FAIRFIELD - FAIRFIELD

  • Developer - Grocon
  • Architect - Jackson Clements Burrows
  • Builder - Atelier Projects
  • No. Dwellings - 75 Townhouses 

Project Update

  • Expected Construction Completion: 4th Quarter 2018
  • Expected Settlement: 4th Quarter 2018
  • Contact: matthew@settlement-solutions.com.au

June 2018

Greenwich Fairfield is seeing exciting activity with the main structure of the building now complete.


HEDGELEY - MALVERN EAST

  • Developer - Little Projects
  • Architect - Adeb Architects with SJB Architects
  • Builder - Hutchinson Builders
  • No. Dwellings - 117 

Project Update

  • Expected Construction Completion: Late 2018
  • Expected Settlement: Late 2018
  • Contact: settlements@littleprojects.com.au

June 2018

Construction at Hedgeley Malvern East is progressing well with the second pour of level 4 complete. With just one level left to pour, once level 4 is finished, the building's structure will soon be complete.


HOLME - COLLINGWOOD 

  • Developer - Cbus Property
  • Architect - John Wardle Architects
  • Builder - Hacer Group Pty Ltd 
  • No. Dwellings - 154 Apartments

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: Mid 2019
  • Contact: clinhart@360propertygroup.com.au

April 2018

Head contractor Hacer continue to impress on site with the site retention now fully completed and excavation works well advanced.


HUNTER - PRAHRAN

  • Developer - ITUM
  • Architect - BG Architecture
  • Builder - Platcon
  • No. Dwellings - 92 

Project Update

  • Expected Construction Completion: Late April 2019
  • Expected Settlement: Late May 2019
  • Contact: clinhart@360propertygroup.com.au

February 2018

Basement retention piling around the perimeter of the basement is complete and capping beams are in progress. Bulk excavation of soil to reveal the basement has also now been completed.


Mckinnon Place

 

Mckinnon Place - Mckinnon

  • Developer - Citiplan
  • Architect - BG Architecture
  • Builder - Bayside Construct
  • No. Dwellings - 23 

Project Update

  • Expected Construction Completion: July 2018
  • Expected Settlement: August 2018
  • Contact: settlements@citiplan.com.au

June 2018

Bayside Construct have continued to make good progress on site with the following works having now been completed:


New Charsfield

 

New Charsfield - Melbourne

  • Developer - EBG Developments
  • Architect - Hecker Guthrie
  • Builder - Hamilton Marino Builders
  • No. Dwellings - 125 

Project Update

  • Expected Construction Completion: Early 2019
  • Expected Settlement: Early 2019
  • Contact: settlements@newcharsfield.com.au

July 2018

New Charsfield has been a hub of activity over the last few months with lifecore now reaching new heights up to level 12-13.


 

No 1 Porter Street

No 1 Porter ST - Hawthorn East

  • Developer - Blueprint Projects
  • Architect - Elenberg Fraser
  • Builder - Buxton Construction
  • No. Dwellings - 88 

Project Update

  • Expected Construction Completion: Late 2018
  • Expected Settlement: Late 2018
  • Contact: monique@settlement-solutions.com.au

June 2018 

Residences are looking fabulous with kitchens and bathrooms now being completed on the lower floors. 


 

 

ORION - BRAYBROOK 

  • Developer - Stockland 
  • Architect - DKO Architecture 
  • Builder - TBA
  • No. Dwellings - 422 Townhomes 

Project Update

  • Expected Construction Completion: Mid 2019
  • Expected Settlement: From Mid 2019
  • Contact:  townhomesettlements@stockland.com.au

June 2018 

We are pleased to advise that construction at Orion Braybrook is progressing well, with civil works well underway for Stage 1.


PRINCE EDWARD RESIDENCES - McKINNON

  • Developer - Platinum
  • Architect - Taylor Reynolds
  • Builder - Platinum Constructions
  • No. Dwellings - 9

Project Update

  • Expected Construction Completion:Mid-2019
  • Expected Settlement:Mid-2019
  • Contact: clinhart@360propertygroup.com.au

July 2018

We are excited to announce that Platinum Constructions have been appointed to build Prince Edward Residences. Onsite, the existing dwellings have now been demolished.


 

 

PROSPECT - PASCOE VALE

  • Developer - ID_Land 
  • Architect - Rothelowman
  • Builder - Shape Homes 
  • No. Dwellings - 7

Project Update

  • Expected Construction Completion: 2nd Quarter 2019
  • Expected Settlement: 2nd Quarter 2019 
  • Contact: clinhart@360propertygroup.com.au

March 2018

We are excited to announce that civil works have commenced on site for Prospect, with sewer works well underway to prepare for Shape Homes to commence construction works on the development. 


 

QA

 

QueenS AVENUE - Hawthorn

  • Developer - Urban
  • Architect - CHT Architects
  • Builder - Orange Building Solutions
  • No. Dwellings - 72 

Project Update

  • Expected Construction Completion: May 2018
  • Expected Settlement: July 2018
  • Contact: clinhart@360propertygroup.com.au

June 2018

We are pleased to advise that Queens Avenue Hawthorn is now complete with Purchaser Inspections now ready to be booked.


 

RA

ROSSLYN APARTMENTS - West Melbourne

  • Developer - Starland Pacific
  • Architect - The Buchan Group
  • Builder - LU Simon
  • No. Dwellings - 165 

Project Update

  • Expected Construction Completion: Quarter 2 2019
  • Expected Settlement: Quarter 2 2019
  • Contact: clinhart@360propertygroup.com.au

June 2018

We are pleased to advise that L.U.Simon are making great progress on site with the following milestones having been achieved through Q2 of 2018:


 


The AlexandRA - KEW

  • Developer - Franze Developments
  • Architect - Hecker Guthrie
  • No. Dwellings - 24 Apartments
 

Project Update

  • Expected Construction Completion: September 2018
  • Expected Settlement: September 2018
  • Contact: clinhart@360propertygroup.com.au

October 2017

Construction is now progressing well on The Alexandra after some earlier delays, but excavations and basement works are well underway.


The Grove

 

The Grove - Brunswick West

  • Developer - Blue Earth Group
  • Architect - Map Architects
  • No. Dwellings - 325 across three buildings (Elm 95; Maple 115; Oak 115) 

Project Update

  • Expected Construction Completion: Late 2019
  • Expected Settlement: Late 2019
  • Contact: kim@blueearth.com.au

March 2018

The Grove is progressing ahead of schedule thanks to the hard work of Hamilton Marino who have already completed piling works and are currently in the process of excavation works.


The International

The International - Melbourne

  • Developer - Blue Earth Group
  • Architect - CHT Architects
  • No. Dwellings - 168

Project Update

  • Expected Construction Completion: Mid 2018
  • Expected Settlement: Mid-July 2018
  • Contact: kim@blueearth.com.au

June 2018

We are pleased to advise that settlement has now been called for The International. Settlement will take place in accordance with individual Contract of Sale terms.


 

THE WALTER - Hadfield

  • Developer - ID Land
  • Architect - Peddle Thorp
  • Builder - Shape Homes
  • No. Dwellings - 64 Townhouses 

Project Update

  • Expected Construction Completion: Third Quarter 2019
  • Expected Settlement: Third Quarter 2019
  • Contact: clinhart@360propertygroup.com.au

May 2018

The Walter has been a hive of activity over the last few months with civil works progressing well. With services now installed and kerb starting to be poured, the developer is expecting that civil will be completed in early June. Thereafter, the builder, Shape Homes, are expected to commence on site.


Make an Enquiry

Spinner